INSTALLATION OF NEW WATER NETWORK CHINGOLA RIVERSIDE EXTENSION

Client: Mulonga Water & Sewerage Company Ltd

Duration:7 Months

Year: 2013

The project was undertaken from March, 2013 to November, 2013.

The scope of the project was Excavation of Trenches, Installation of Pipes, Valves, Fire Hydrants, Water Meters and associated fittings. The total distance covered during this project was 12Kilometers covering 800 housing units. The project was executed and commissioned successfully.

Main stream trench Size: 1.2m x 0.6m
Household trench size: 0.6m x 0.5
PVC Pipe Size: 1’’, 2’’, 3’’, 4’’, 6’’ and 8’’

REHABILITATION, ASSEMBLY, INSTALLATION & COMMISSIONING OF BALL MILL

Client: Chambishi Metals Plc

Duration: 3 Months

Year: 2017

The Ball Mill was installed for grinding of Lime.


REHABILITATION, INSTALLATION & COMMISSIONING OF CONVEYOR

Client: Chambishi Metals Plc

Duration: 2 Months

Year: 2015

Designed and fabricated to collect materials from the Belt Filter at Cobalt Plant.


REHABILITATION OF GATE VALVES, DIAPHRAGMS VALVES, PLUG VALVES, KNIFE GATE & BUTTERFLY VALVES

Client: : Chibuluma Mines, Chambishi Metals & Ndola Lime


RECLAIM, DISMANTLING, REHABILITATION AND INSTALLATION OF EVAPCO COOLING TOWERS

Client: Chambishi Metals Plc

Duration: 6 Months

Year: 2014

After the successful completion of this project at Acid plant, the refurbished cooling Towers are now able to lower the temperatures from as high as 100 degrees Celsius to as low as 17 degrees Celsius for desired processes.


Client: : Chambishi Metals Plc

Application: : For Acidic Fumes and High Temperatures

Client: : Chibuluma Mines Plc

Application: : Sump pumps/High lift